  • Within 14 days after completion of an inspection made under AS 09.45.885, the construction professional shall serve on the claimant a written
            (1) offer to repair the defect without charge to the claimant; the offer must include a report of the scope of the inspection, the findings and results of the inspection, a description of any repairs necessary to repair the defect, and a schedule for the completion of the repairs;
            (2) offer to compromise and settle the claim by a payment of money under AS 09.45.882(b)(2); or
            (3) statement that the construction professional will not repair the defect.

Authorities

9.45.887; 9.45.888; 9.45.889; 9.45.890

Notes


References

AS 9.45.887 .887">Sec. 09.45.887. Court action allowed after failure to repair or to settle.
AS 9.45.888 .888">Sec. 09.45.888. Court action allowed if claimant rejects offer.
AS 9.45.889 .889">Sec. 09.45.889. Unreasonable rejection of offer.
AS 9.45.890 .890">Sec. 09.45.890. Acceptance of offer.
History

(Sec. 3 ch 136 SLA 2003)