Section 35.15.110. Title to site and completion of project.  


Latest version.
  •    (a) Before advertisement for bids or construction contract negotiations, the department shall approve both the project site and the land interest in the site.
       (b) Responsibility for maintenance of the project shall be established in the original contract agreement. The department shall participate in the final inspection of the project and approve of the final documents on the project.

Notes


Implemented As

17 AAC 55.070
History

(Sec. 1 ch 57 SLA 1976; am Sec. 1 ch 62 SLA 1978; am Sec. 9 ch 147 SLA 1978; am Sec. 51 ch 35 SLA 2003)