Section 46.14.140. Emission control permit program regulations.  


Latest version.
  •    (a) The department shall adopt regulations to address substantive and procedural elements of the emission control permit program established under this chapter that are not addressed in statute, except elements that relate only to the internal management of the department and do not affect the public or govern the way the department deals with the public. The regulations must be reasonable and adequate, and provide flexibility in the operation of a stationary source consistent with 42 U.S.C. 7401 - 7671q (Clean Air Act), as amended, and applicable federal regulations. Except for regulations concerning minor permits required under AS 46.14.130(c), the regulations must include
            (1) a standard permit application form that meets the requirements of federal regulations adopted under 42 U.S.C. 7661a(b) (Clean Air Act, sec. 502(b));
            (2) monitoring, record keeping, and reporting requirements for facilities that are subject to AS 46.14.130(b), which must comply with the requirements established for state operating permit programs in 40 C.F.R. 70.6, but which may be modified to take into account this state's unique conditions;
            (3) procedures for preparation and submission of a monitoring, reporting, and quality assurance plan and, if required, a compliance schedule describing how a permitted stationary source will comply with the applicable requirements of this chapter;
            (4) procedures for
                 (A) specifying when permit applications and renewal requests are to be submitted;
                 (B) specifying the time duration for department review of permit applications;
                 (C) processing and reviewing an application;
                 (D) providing public notice, including opportunity for public comment and hearing; and
                 (E) issuing permits, including procedures for issuing permits for temporary operations or open burn activities;
            (5) reasonable standard permit conditions, including conditions for
                 (A) emission standards and limitations;
                 (B) monitoring, record keeping, and reporting for facilities subject to AS 46.14.130;
                 (C) inspection and entry;
                 (D) certification of corporate or other business organization reports;
                 (E) annual certification of compliance;
                 (F) excess emission or process deviation reporting; and
                 (G) equipment malfunctions and emergencies;
            (6) fees and procedures for collecting fees;
            (7) provisions addressing late payment or nonpayment of fees, which may include assessment of penalties and interest or refusal to issue, amend, modify, or renew an air quality control permit;
            (8) the duration of permits;
            (9) procedures for modifying or amending a permit that provide flexibility in the operation of the stationary source, including procedures to allow changes to a permitted stationary source without requiring a permit modification, consistent with the purposes of this chapter and with 42 U.S.C. 7401 - 7671q (Clean Air Act);
            (10) reasonable provisions for renewing, reopening, revoking and reissuing, and terminating a permit consistent with the purposes of this chapter and 42 U.S.C. 7401 - 7671q (Clean Air Act);
            (11) provisions allowing for physical or operational limitations that will reduce a stationary source's emissions to levels below those that would make the stationary source subject to part or all of AS 46.14.120 and 46.14.130;
            (12) provisions authorizing stationary source operation while a permit application is pending, consistent with 42 U.S.C. 7661b(d) (Clean Air Act, sec. 503(d));
            (13) provisions for ensuring that compliance with an operating permit issued under this chapter will be considered to be compliance with 42 U.S.C. 7661a (Clean Air Act, sec. 502) and other provisions of state or federal law specifically provided for by the department consistent with 42 U.S.C. 7401 - 7671q (Clean Air Act) and regulations adopted under state and federal law;
            (14) provisions allowing for certification of inspectors who evaluate compliance with the terms and conditions of a permit, order, regulation, or other provision of law authorized under this chapter; and
            (15) definitions of terms incorporating applicable definitions in 42 U.S.C. 7401 - 7671q (Clean Air Act), as amended, and applicable federal regulations, to the extent that those definitions are not inconsistent with this chapter.
       (b) A permit issued under this chapter may not require a person to use
            (1) machinery, devices, or equipment of a particular type, from a particular supplier, or produced by a particular manufacturer; or
            (2) specific methods, processes, procedures, or designs for the management and operation of a stationary source regulated under this chapter except to the extent that the federal administrator has
                 (A) adopted a design, equipment work practice, or operational standard under 42 U.S.C. 7412(h), as amended, for the control of a hazardous air pollutant; or
                 (B) approved an alternative hazardous air pollutant standard under 42 U.S.C. 7412(h)(3), as amended.
       (c) The absence of, or the department's failure to adopt, a regulation under this section does not relieve a person from compliance with a permit issued under this chapter and with other provisions of law, including emission control requirements.

Authorities

46.14.120;46.14.160;46.14.170;46.14.260;46.14.265;46.14.285;46.14.515;46.14.560

Notes


Implemented As

18 AAC 15.190
18 AAC 50.030
18 AAC 50.035
18 AAC 50.205
18 AAC 50.215
18 AAC 50.220
18 AAC 50.225
18 AAC 50.235
18 AAC 50.240
18 AAC 50.301
18 AAC 50.302
18 AAC 50.306
18 AAC 50.311
18 AAC 50.316
18 AAC 50.326
18 AAC 50.345
18 AAC 50.346
18 AAC 50.400
18 AAC 50.403
18 AAC 50.410
18 AAC 50.420
18 AAC 50.430
18 AAC 50.499
18 AAC 50.502
18 AAC 50.508
18 AAC 50.510
18 AAC 50.540
18 AAC 50.542
18 AAC 50.544
18 AAC 50.546
18 AAC 50.560
18 AAC 50.990
References

AS 46.14.120 Permits for construction, installation, modification, or operation.
AS 46.14.160 Completeness determination.
AS 46.14.170 Administrative actions regarding permits.
AS 46.14.260 Clean air protection fund.
AS 46.14.265 Emission control permit receipts account.
AS 46.14.285 Amendment and modification of permit upon request of permittee.
AS 46.14.515 Inspection.
AS 46.14.560 Unavoidable malfunctions and emergencies.
History

(Sec. 2 ch 74 SLA 1993; am Sec. 15, 16 ch 46 SLA 2003; am Sec. 3 ch 33 SLA 2005)