Section 46.14.230. Duration of operating permits.  


Latest version.
  •    (a) An operating permit under this chapter, including an operating permit that contains a compliance schedule, shall be issued for a fixed term of five years after the date of issue, except as provided for temporary operations under AS 46.14.215 or unless a shorter term is requested by the permit applicant.
       (b) If a timely and complete application for renewal of an operating permit is submitted to the department, the existing permit issued under this chapter does not expire until the renewal permit has been issued or denied.

Notes


Implemented As

18 AAC 50.301
18 AAC 50.326
18 AAC 50.990
References

18 AAC 50.301
18 AAC 50.326
History

(Sec. 2 ch 74 SLA 1993)